LOI Signing

Signed by both seller and company

Status

Civil Engineer Hiring

We have sent our RFP to multiple local civil engineering companies, hoping to get Civil Engineers at work by Oct 14th

Status

Land Use Application

The Propinvest-ROI team, along with engineering consultants, gathers site information to create the Land Use Application.

  • Boundary Survey
  • Topography and Traffic Study
  • Vicinity/Circulation Mapping
  • Existing Conditions Mapping
  • Preliminary Utility Plan
  • Preliminary Grading, Drainage, and Erosion Control Plan
  • Storm Water Report
  • Landscape/Mitigation/Tree Preservation Plan
  • Written Application Narrative

Status

Signing Of PSA

Status

Application Submission & Review

  • May include hearings
  • Officer review
  • Planning commission approval
  • City council approval

Status

Bexar County Approval Process

18-24 months. (MDP** could be a shorter timeline) As of 1/10/25

Status

SAWS (San Antonio Water System)

6-9 months. As of 1/10/25

Status

TCEQ (Texas Commission on Environmental Quality)

6-9 months.. As of 1/10/25

Status

City of San Antonio

2-3 months. As of 1/10/25

Status

Commissioner's Approval

6-9 months. As of 1/10/25

Status

preliminary plat approval

Engineers are quoting this process as much faster than 18-24 months through Bexar County.

Status